2. Master rule

  1. Scale the rigor of every rule to (consequence of failure) × (uncertainty).
  2. Keep reducing risk until the cost of the next reduction is grossly disproportionate to the benefit (ALARP).
Risk region Required action
unacceptable risk must be reduced, whatever the cost
tolerable reduce risk while it is reasonably practicable (ALARP)
negligible no further reduction is required

In management, the same idea has three established names:

Engineering term Management term Source
scale the rigor tailoring: adapt the method to the size, risk and context of the work PRINCE2 principle 7 "Tailor to suit the project"; PMBOK Guide 8th edition "Tailor for your context"
boundary between the unacceptable and the tolerable region risk appetite: the amount and type of risk the governing body accepts in pursuit of its objectives COSO ERM 2017, principle 7 "Defines Risk Appetite"
consequence impact on people, money, legal position, reputation and objectives; irreversibility raises the consequence ISO 31000:2018; Amazon 2015 shareholder letter (one-way doors)